The entrance to site was shared with the entrance to the already existing warehouse, operating using a one-way system, calling for meticulous coordination on deliveries, considering pedestrians and working hours. Partial handover was also planned to ensure the client always had access to 50% of their yard, minimising disruption to production.
Before the team could begin, they carried out the removal of existing buildings that were partly demolished and buried underneath the ground. This involved breaking out and carefully segregating waste, some of which went to a specialist removal centre.
GB Lubricants
Client: GB Lubricants
Sector: Industrial
Contract Type: JCT
After many years of repeat business, Meldrum Civil Engineering were contracted to construct a warehouse and maintenance building for GB Lubricants.
The new warehouse is being utilised for storage whilst the maintenance building has been converted to a workshop with office space.