A19 WOLVISTON

CASE STUDIES

Project Description

Meldrum Civil Engineering were appointed to carry out roadworks on the A19 layby adjacent to Wolviston junction for Sir Robert McAlpine.

The project was delivered over a 12-week period comprising of night shifts during the week and on weekends.

Night shift operations comprised of –

  • Cutting the existing concrete road into 1x 1.2 sections in preparation for the carriageway to be excavated on the weekend.
  • Break up and removal of 200m long x 3m wide layby, with topsoil reinstatement.
  • Break out and reinstatement of the existing kerb line, drainage channels, gullies and manholes to allow for the overlay of the existing carriageway.

Machinery used: –

  • 20 t Excavator with height restrictor
  • JCB 3CX with vacuum kerb lifter
  • Hi Ab
  • Grab Wagon
  • Wagons

Special requirements –

Works were carried out on night closures which had to be delivered within strict timescales.  All works were closely coordinated with other trades to ensure that follow-on trades could install works within pre described night shift hours.  Deliveries to site had to be managed to ensure the optimum utilisation of labour and plant, this resulted in the reliance of specialist supply chains to supply concrete. Standards of site cleanliness were strictly maintained as the carriageway needed to be clear and free of construction debris for the following day.

Weekend works had to be completed to tight timescales with 35-40 wagons loads of pre-cut concrete slabs loaded before 4 pm to ensure installation and curing of tarmac to be completed in sufficient time for the A19 to reopen on Monday mornings.  Works were carried out over 8 weekends with 4 of the weekends witnessing excavation under interchange bridges requiring height restrictor on plant.

AT A GLANCE

Value

£1.4m

Client

SIR ROBERT MCALPINE